Interconnection Process

Westlands Water District administers all interconnection requests to the WWD Transmission System pursuant to its Transmission Owner Access Policy (TOAP) and Large Generator Interconnection Procedures (LGIP).

Interconnection requests to the WWD Transmission System are administered by Westlands Water District (WWD) pursuant to its Transmission Owner Access Policy (TOAP) and Large Generator Interconnection Procedures (LGIP). WWD utilizes a structured, cluster-based interconnection process designed to evaluate eligible projects efficiently, consistently, and transparently.

Applicants should review all governing materials and submission requirements before applying. Additional materials will be posted in advance of each interconnection request window.

Interconnection Requests

Request windows, technical materials, and submission instructions will be posted in advance of each application cycle. Expected notices include:

  • Application Window: June 15 – June 26
  • Advance Notice Period: Materials and technical requirements will be posted prior to the opening of the request window.
  • Updates: This page will be updated as schedules are finalized.

How It Works

1
Prepare

Review Requirements and Prepare Application

Applicants should confirm project eligibility, review all policies and procedures below, and prepare all required technical and application materials prior to submission.

Register Interconnection Interest Now
2
Submit

Submit Application During Request Window

Complete applications are accepted only during the designated interconnection request window.

Partner Portal
3
Validate

Validation

Applications are reviewed and evaluated as part of a cluster study.

4
Study

Cluster Study

Eligible applications are grouped and evaluated together as part of a cluster study process.

5
Results

Study Results and Next Steps

Applicants receive study findings and guidance on next steps.

Updates

Page updated as materials and timelines are finalized. Last Updated: 05/01/2026

Questions?

Contact the VCIP interconnection team.